Question #: 85
Topic #: 9

You are the project manager for the GHY Organization. A stakeholder has presented a change to your project that will cause the project scope to increase considerably. You are considering the change for approval and you need to review the impact of the change on all areas of the project. What change control system component is responsible for guiding the review of the impact of all changes on the project management knowledge areas?


A.

Scope change control system


B.

Change control system


C.

Configuration management


D.

Integrated change control