GIAC Security Leadership Certification (GSLC) GSLC Question # 83 Topic 9 Discussion

GIAC Security Leadership Certification (GSLC) GSLC Question # 83 Topic 9 Discussion

GSLC Exam Topic 9 Question 83 Discussion:
Question #: 83
Topic #: 9

You are working in a functional organization and are managing the IHH Project. Your project will likely last for six months and has a budget constraint of $1,876,000. You'll be dealing with a functional manager to manage costs and resources in the project. Who will have authority over assigning the project team members to activities?


A.

Customers


B.

Project sponsor


C.

Functional manager


D.

Team leader


Get Premium GSLC Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.