CDT Exam Topic 2 Question 19 Discussion:
Question #: 19
Topic #: 2

For a large transportation project, 53 borings were made and only one boring showed some contamination. Due to financial constraints, the owner is unable to provide additional funding to the design team for further investigation. Which of the following is the best course of action for the design team?


A.

Withhold the information from the bid package because the full extent remains unknown. Ask bidders to provide a unit cost for remediation.


B.

Provide a disclaimer on the contract documents about potential contaminants onsite and suggest the owner make the geotechnical report available to all bidders.


C.

Insist the owner undertake additional investigation to determine the full extent prior to putting the project out for bid.


D.

Proceed with design as is without any modifications since the results are statistically insignificant (i.e., well within expected deviations).