New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

Construction Specifications Institute Construction Documents Technologist CDT Question # 18 Topic 2 Discussion

Construction Specifications Institute Construction Documents Technologist CDT Question # 18 Topic 2 Discussion

CDT Exam Topic 2 Question 18 Discussion:
Question #: 18
Topic #: 2

What project scheduling technique involves setting the target date of building occupancy and then working backwards to establish preceding milestone dates?


A.

Methods technique


B.

Critical path method


C.

Front end loading


D.

Schedule of values


Get Premium CDT Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.