CDT Exam Topic 1 Question 6 Discussion:
Question #: 6
Topic #: 1

In which project phase would outline specifications be created in order to be used as a checklist for further development of the project documents?


A.

Project Conception phase


B.

Schematic Design phase


C.

Design Development phase


D.

Construction Documents phase