An architect/engineer (A/E) is reviewing a claim from a contractor asking for more money and time on the project. The A/E plans to reject this claim based on documentation supplied by the contractor indicating what reason?


A.

There was active interference by the owner.


B.

There were conditions beyond the control of the contractor or owner.


C.

The A/E modified the contract documents.


D.

There is defective work needing repair.