CompTIA Project+ Certification (2025) PK0-005 Question # 14 Topic 2 Discussion

CompTIA Project+ Certification (2025) PK0-005 Question # 14 Topic 2 Discussion

PK0-005 Exam Topic 2 Question 14 Discussion:
Question #: 14
Topic #: 2

A project team evaluated the performance of a new reporting system and the quantity of queries to be processed during predetermined time stamps.

PK0-005 Question 14

Which of the following is the current status of the process?


A.

Based on the rule of seven, the process is under control


B.

The amount of data is insufficient to determine if quality is low.


C.

The process is out of control and should be revised.


D.

The goal should be adjusted since most of the data points are close to the lower limit.


Get Premium PK0-005 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.