PK0-005 Exam Topic 2 Question 15 Discussion:
Question #: 15
Topic #: 2

A lessons-learned meeting took more than two hours and ended without defining a standardized process. The project manager decides to move forward without allowing changes to the existing process. Which of the following techniques is the project manager using?


A.

Forcing


B.

Avoiding


C.

Compromising


D.

Smoothing