Big 11.11 Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

CIPS Commercial Contracting L4M3 Question # 16 Topic 2 Discussion

CIPS Commercial Contracting L4M3 Question # 16 Topic 2 Discussion

L4M3 Exam Topic 2 Question 16 Discussion:
Question #: 16
Topic #: 2

Maximum Score: 1

An urgent component requirement needs to be purchased to meet the timescales of a project. A supplier proposes using its standard terms and conditions. What risk to the buying organisation could this bring?


A.

A breach of competition laws


B.

Contract conditions that are favourable to the buyer


C.

A breach of the supplier's internal financial controls


D.

Contract conditions that are favourable to the supplier


Get Premium L4M3 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.