Projects carried out using the PRINCE2 methodology are always set out in a series of distinct and sequential stages. Which of the following is NOT a valid reason for a planned break between stages?
A.
The project team is required to break and regroup ready for the next package of work.
B.
The project board can make a decision as to whether the project business case is still viable.
C.
The progress of the project can be reviewed to ensure this justifies the continuation of the project.
D.
Risks to the project can be reassessed before further commitments of money or resources.