CIMA Project and Relationship Management E2 Question # 59 Topic 6 Discussion

CIMA Project and Relationship Management E2 Question # 59 Topic 6 Discussion

E2 Exam Topic 6 Question 59 Discussion:
Question #: 59
Topic #: 6

As part of a project to refurbish a large hotel chain, the wiring of the computer network was subcontracted to a specialist IT organisation. In relation to managing risk in the project this approach can be referred to as:


A.

Reduce


B.

Avoid


C.

Transfer


D.

Accept


Get Premium E2 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.