A program to implement a new payroll processing system at a healthcare company is nearing completion and is under budget. What should the program manager do next?
A.
Request permission from the program governance board to initiate program closure activities
B.
Present additional opportunities to the program sponsor
C.
Apply the remaining budget to operational activities
D.
Apply the remaining budget to deferred enhancement requests
Chosen Answer: