A formal Requirements Validation Review (or walkthrough/inspection) is conducted to ensure the requirements are correct, complete, and meet the business need before sign-off. The review group typically includes the Business Owner (A) to ensure correctness, the Solution Architect (C) and Developers to check technical feasibility, and the Tester (D) to ensure testability. The Project Manager (B) is usually the facilitator or organiser of the review process and is responsible for project delivery, but they are NOT usually a technical reviewer of the document content itself, as their direct involvement could compromise the impartiality of the review, which is focused on quality assurance, not project schedule.