BCS Foundation Certificate in IS Project Management ISEB-PM1 Question # 175 Topic 18 Discussion

BCS Foundation Certificate in IS Project Management ISEB-PM1 Question # 175 Topic 18 Discussion

ISEB-PM1 Exam Topic 18 Question 175 Discussion:
Question #: 175
Topic #: 18

The sponsor is worried about the seller deriving extra profit on the cost plus fixed fee (CPFF) contract. Each month the sponsor requires the project manager to submit CPI calculations and an analysis of the cost to complete. The project manager explains to the sponsor that extra profits should NOT be a worry on this project because:


A.

The team is making sure the seller does not cut scope.


B.

All costs invoiced are being audited.


C.

There can only be a maximum 10 percent increase if there is an unexpected cost overrun.


D.

The fee is only received by the seller when the project is completed.