Which of the following lists contain processes that are included within Project Procurement Management?


A.

Plan purchases and acquisitions, plan contracting, request seller responses, select sellers


B.

Plan purchases and acquisitions, request seller responses, select sellers, schedule control


C.

Plan purchases and acquisitions, acquire project team, request seller responses, select sellers


D.

Plan purchases and acquisitions, acquire project team, contract approval, select sellers