BCS Foundation Certificate in IS Project Management ISEB-PM1 Question # 120 Topic 13 Discussion

BCS Foundation Certificate in IS Project Management ISEB-PM1 Question # 120 Topic 13 Discussion

ISEB-PM1 Exam Topic 13 Question 120 Discussion:
Question #: 120
Topic #: 13

Which of the following lists contain processes that are included within Project Procurement Management?


A.

Plan purchases and acquisitions, plan contracting, request seller responses, select sellers


B.

Plan purchases and acquisitions, request seller responses, select sellers, schedule control


C.

Plan purchases and acquisitions, acquire project team, request seller responses, select sellers


D.

Plan purchases and acquisitions, acquire project team, contract approval, select sellers


Get Premium ISEB-PM1 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.