BCS Foundation Certificate in IS Project Management ISEB-PM1 Question # 119 Topic 12 Discussion

BCS Foundation Certificate in IS Project Management ISEB-PM1 Question # 119 Topic 12 Discussion

ISEB-PM1 Exam Topic 12 Question 119 Discussion:
Question #: 119
Topic #: 12

You are in the middle of a major new facility construction project. The structural steel is in place and the heating conduits are going into place when a senior manager informs you that he is worried that the project will not meet the quality standards.

What should you do in this situation?


A.

Assure senior management that during the Plan Quality process it was determined that the project would meet the quality standards.


B.

Analogously estimate future results.


C.

Form a quality assurance team.


D.

Check the results from the last quality management plan.


Get Premium ISEB-PM1 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.