BCS Foundation Certificate in IS Project Management ISEB-PM1 Question # 112 Topic 12 Discussion
ISEB-PM1 Exam Topic 12 Question 112 Discussion:
Question #: 112
Topic #: 12
Resource leveling _____________.
A.
Attempts to reduce resource requirements within a constraint on project duration
B.
Smooths out resource requirements by rescheduling activities within their float time.
C.
Allocates resources to activities to find shortest schedule within fixed resource limits.
D.
Smooths out resource requirements by substituting activities with unassigned resources.
E.
1) Smooths out resource requirements by rescheduling activities within their float time, or 2) Attempts to reduce resource requirements within a constraint on project duration
Chosen Answer:
This is a voting comment (?). You can switch to a simple comment. It is better to Upvote an existing comment if you don't have anything to add.