Formal written correspondence is mandated in which of the following situations:
Client requests additional work not covered under contract
None of the other alternatives apply
Both 1) Client requests additional work not covered under contract, and 2) Project manager calls a meeting.
Project manager calls a meeting
Product undergoes casual in-house testing