Question #: 20
Topic #: 3

IT services has commissioned a new desktop PC replacement project that has been funded and running for three months, with a fully-engaged sponsor and programme manager appointed

The head of IT services has not been involved beyond the initial project start-up interviews and has not attended any of the project meetings

What position on the power interest and does the head of IT services currently occupy?


A.

High power or influence but low interest


B.

Some power and influence and some interest


C.

High power or influence and high interest


D.

Low power and influence but high interest