BCS Practitioner Certificate in Business Analysis Practice v5.2 BAPv5 Question # 20 Topic 3 Discussion

BCS Practitioner Certificate in Business Analysis Practice v5.2 BAPv5 Question # 20 Topic 3 Discussion

BAPv5 Exam Topic 3 Question 20 Discussion:
Question #: 20
Topic #: 3

A business analyst is reviewing the stakeholder management strategy for a project seeking to implement a new IT system to monitor the effectiveness of social work interventions. Three stakeholders have been identified.

1. Head of Monitoring and Evaluation is the project sponsor

2. The monitoring and evaluation officer working in the Head of Monitoring and Evaluation's team who is eager to get the project implemented as it will transform his role

3 The financial accountant assigned to the project to monitor the financial benefits of the new system This role is essential to the project, but he isn't interested in the detail.

The analyst has identified stakeholder management strategies for two of the three stakeholders 'active and constant management' and 'keep onside'

Based on the information presented in the scenario, which further strategy is required?


A.

Keep satisfied


B.

Watch


C.

Ignore


D.

Keep informed