AVIXA Certified Technology Specialist CTS Question # 67 Topic 7 Discussion

AVIXA Certified Technology Specialist CTS Question # 67 Topic 7 Discussion

CTS Exam Topic 7 Question 67 Discussion:
Question #: 67
Topic #: 7

In order to estimate project task duration, one needs to understand the effort required to complete the expected scope and:


A.

Client budget


B.

User experience


C.

Required training


D.

Resource availability