AVIXA Certified Technology Specialist CTS Question # 36 Topic 4 Discussion

AVIXA Certified Technology Specialist CTS Question # 36 Topic 4 Discussion

CTS Exam Topic 4 Question 36 Discussion:
Question #: 36
Topic #: 4

A client requests for a project to be completed earlier than initially scheduled. What should the AV contractor do FIRST to address this change?


A.

deny the request and work to the original agreed schedule


B.

allocate more resources to meet the earlier completion date


C.

provide a request for change (RFC) to the client to approve the change to the schedule


D.

provide a change order (CO) to the client outlining changes to the project and any additional costs


Get Premium CTS Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.