When a client requests an earlier project completion date, the AV contractor should first issue a Request for Change (RFC). This formal request documents the proposed schedule change and requires client approval. It allows for assessment of resource requirements, timeline adjustments, and any potential cost implications.
CTS Technology Specialist Reference
The CTS guidelines stress documenting changes through formal requests like RFCs to ensure client approval and clarity on any impact to the project.