A crucial part of the bid (tender) process is the request for clarification. At what point in the bid (tender) process would a potential bidder submit a request for clarification?
A.
After the award, but before the job begins
B.
After proposals are submitted, but before the award
C.
After the bid (tender) specifications are received, but before the proposals are due
D.
After the walkthrough, but before the bid (tender) specification package is sent out
Requests for clarification are typically submitted after receiving the bid specifications but before the proposal submission deadline. This allows potential bidders to seek additional information or clarification on the project requirements to prepare accurate and comprehensive proposals.