A crucial part of the bid (tender) process is the request for clarification. At what point in the bid (tender) process would a potential bidder submit a request for clarification?


A.

After the award, but before the job begins


B.

After proposals are submitted, but before the award


C.

After the bid (tender) specifications are received, but before the proposals are due


D.

After the walkthrough, but before the bid (tender) specification package is sent out