For a design-bid (tender)-build project, the final step for determining the owner's costs for an AV system is ensuring the equipment specification is ready for bid. This step involves finalizing all equipment details, specifications, and requirements so that accurate bids can be obtained from potential contractors. Axis documentation indicates that having precise and detailed equipment specifications is critical for obtaining accurate project costs and selecting the best contractor for the job.