Analyze the Epic Report shown.

ACP-610 Question 13

Identify why the epic completion date is hard to predict.


A.

Most stories aren't estimated until the end of the epic


B.

The configured Working Days for the board are unrealistic.


C.

The team is using issue count for their estimation statistic.


D.

The team adds new stories throughout the epic.