ATLASSIAN Managing Jira Projects for Data Center and Server Certification ACP-610 Question # 12 Topic 2 Discussion

ATLASSIAN Managing Jira Projects for Data Center and Server Certification ACP-610 Question # 12 Topic 2 Discussion

ACP-610 Exam Topic 2 Question 12 Discussion:
Question #: 12
Topic #: 2

The release manager is requesting a list of all issues included in a particular sprint. Which report will provide this information?


A.

Control Chart


B.

Release Burndown


C.

Version Report


D.

Sprint Report


E.

Average Age Report


Get Premium ACP-610 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.