Your team uses Story Points for estimation and tracking.

You performed several actions in the active sprint.

Which two actions are reflected as scope change? (Choose two.)


A.

Added a fix version on a committed story.


B.

Estimated a story in the backlog.


C.

Dragged on estimated story from the backlog to the sprint.


D.

Modified the estimate value on a committed story.


E.

Added another 5ub-task to a committed story.


F.

Logged work on several committed stories.