ASIS-CPP Exam Topic 7 Question 63 Discussion:
Question #: 63
Topic #: 7

Whenever possible, security planning for a new facility should begin during which of the following phases?


A.

Floor plan design


B.

Zoning approval


C.

Site selection


D.

Construction