APM Project Management Qualification (PMQ) Exam APM-PMQ Question # 3 Topic 1 Discussion

APM Project Management Qualification (PMQ) Exam APM-PMQ Question # 3 Topic 1 Discussion

APM-PMQ Exam Topic 1 Question 3 Discussion:
Question #: 3
Topic #: 1

You are in the design phase of a project to deliver offices on a newly acquired plot of land. You have now completed extra surveys and discovered that the ground conditions are a lot softer than expected, meaning the design and delivery will be far more complex and costly. You did not account for this in your risk register.

Which of the following statements about the project business case is true?


A.

The business case contained assumptions which should be reviewed against the cost-benefit analysis.


B.

There is a strong strategic case for the project to continue, even if it is late or over budget.


C.

The business case has already been signed off, so the project should continue as planned.


D.

The project sponsor did not properly evaluate all available options in the business case.


Get Premium APM-PMQ Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.