What are two benefits of governance in risk and issue management?
You are a project manager taking over a project that’s in the definition phase. The project sponsor asks you to prepare for an upcoming budget review as they have concerns regarding the lack of cost control shown by the project to date.
Which of the following actions would best improve the project sponsor's confidence in how you will control costs?
You are in the design phase of a project to deliver offices on a newly acquired plot of land. You have now completed extra surveys and discovered that the ground conditions are a lot softer than expected, meaning the design and delivery will be far more complex and costly. You did not account for this in your risk register.
Which of the following statements about the project business case is true?
You have been assigned to manage a new project team. The team has recently been set up to improve service levels which have drastically reduced over the past year.
Only a few of the team members have worked together before. It is your responsibility as the leader to facilitate the team's development.
Question:Identify two models you could use to facilitate developing your team. (2 marks)
Question:Explain three ways team development models can help the team meet their objective to improve service levels. (3 marks)
You are a project manager leading a newly formed project team. Which factor should NOT influence your decision when assigning roles and responsibilities to your team members?
You are overseeing a construction project for a new retail center. Midway through the project, the design team proposes a significant change to the building's layout, which they argue will improve overall functionality and therefore present better value for money. However, this change would require demolishing and rebuilding a section of the structure.
Given the proposed changes, outline five actions you would take to evaluate the change request to provide an appropriate recommendation.
Which of the following statements best describes the purpose of an integrated project management plan?
You are managing a project that is approaching its final phase and is soon to be handed over to the operations team. One of the critical aspects of this transition is the effective engagement of stakeholders.
You are managing a construction project aimed at developing a new eco-friendly office building. You are tasked with ensuring that sustainability measures are effectively monitored and reported.
At which point in the project life cycle should you implement sustainability measures?
You are managing a project to develop and deploy a new finance management software system for a client. The project has been deployed and is now in the post-deployment support phase. This phase requires ongoing technical support and maintenance after the software is deployed. The workload can vary significantly over time, is likely to evolve over time, and quick response times are essential.
Question: Based on the features of different contractual relationships and methods of supplier reimbursement, state the most appropriate contract type for the post-deployment phase. (1 mark)
Question: Explain four reasons why this would be the most suitable. (4 marks)