Question #: 2
Topic #: 1

You are a project manager taking over a project that’s in the definition phase. The project sponsor asks you to prepare for an upcoming budget review as they have concerns regarding the lack of cost control shown by the project to date.

Which of the following actions would best improve the project sponsor's confidence in how you will control costs?


A.

Create a work breakdown structure.


B.

Create a cost breakdown structure.


C.

Create an earned value report.


D.

Create a financial appraisal.