CPIM-8.0 Exam Topic 6 Question 51 Discussion:
Question #: 51
Topic #: 6

The horizon for forecasts that are input to the sales and operations planning (S & OP) process should be long enough that:


A.

cumulative forecast deviation approaches zero.


B.

planned product launches can be incorporated.


C.

required resources can be properly planned.


D.

supply constraints can be resolved.


Get Premium CPIM-8.0 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.