New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

APICS Certified in Planning and Inventory Management (CPIM 8.0) CPIM-8.0 Question # 141 Topic 15 Discussion

APICS Certified in Planning and Inventory Management (CPIM 8.0) CPIM-8.0 Question # 141 Topic 15 Discussion

CPIM-8.0 Exam Topic 15 Question 141 Discussion:
Question #: 141
Topic #: 15

The horizon for forecasts that are input to the sales and operations planning (S&OP) process should be long enough that:


A.

cumulative forecast deviation approaches zero.


B.

planned product launches can be incorporated.


C.

required resources can be properly planned.


D.

supply constraints can be resolved.


Get Premium CPIM-8.0 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.