Question #: 170
Topic #: 18

A company has the following production conditions:

    Batch size: 1,000 items

    Processing time: 4 minutes per item

    Setup time: 2 hours

    Utilization: 80%

    Efficiency: 80%

Which of the following actions would result in the work being done in the least amount of time?


A.

Reduce the processing time for each item to 3.5 minutes.


B.

Increase either utilization or efficiency to 100%.


C.

Increase both utilization and efficiency to 90%.


D.

Eliminate the need for a setup to process the batch.