Labor3 people

Work hours10 hours per day

Days4 days per week

Meetings with work area employees1/2 hour per day

Work area efficiency85%

Given the information above, what is the weekly theoretical capacity of this work area in hours?


A.

97


B.

102


C.

114


D.

120