The labor efficiency variance is the difference between the standard labor hours allowed for the actual output and the actual labor hours used, multiplied by the standard labor rate. In this case, the standard labor hours allowed for 100 pieces are 0.5 * 100 = 50 hours. The actual labor hours used are 48 hours. The standard labor rate is $10 per hour. Therefore, the labor efficiency variance = (50 - 48) * $10 = $20 favorable. This means that the actual labor hours used were less than the standard labor hours allowed, which indicates a higher labor efficiency12 References: 1: CPIM Part 2 - Section B - Module 2 - Session 2 - Variance Analysis 2: CPIM Part 2 - Section B - Module 2 - Session 3 - Variance Analysis Example