After collecting the control information on a light rail project within an original budget of 200.000 work hours, the construction contractor is ready for their monthly progress meeting with the client.

A total of 100.000 work hours have boon scheduled to date. with 105.000 work hours earned, and 110.000 work hours paid. The stated progress by the contractor Is 60%.

What is a method for figuring estimate at completion (EAC)?


A.

BCWP + (BAG - ACWP)


B.

ACWP + (BAC - BCWS)


C.

BCWS + (BAG -ACWP)


D.

ACWP + (BAC - BCWP)