Question #: 23
Topic #: 3

An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.

Answer the question using a straight line depreciation and a 10% interest rate.

Which of the following would NOT be considered part of a project cost and schedule forecast?


A.

Usage of contingency


B.

Current trends of time and money


C.

Peripherals report


D.

Changes to the project execution plan