AACE International Certified Cost Professional (CCP) Exam CCP Question # 11 Topic 2 Discussion

AACE International Certified Cost Professional (CCP) Exam CCP Question # 11 Topic 2 Discussion

CCP Exam Topic 2 Question 11 Discussion:
Question #: 11
Topic #: 2

In a fixed price contract the:


A.

Contractor has no risk in the project


B.

Contactor assumes all the performance risk


C.

Contractor is paid for actual costs


D.

Owner has all the risk


Get Premium CCP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.