Pass the CIPS CIPS Level 4 Diploma in Procurement and Supply L4M3 Questions and answers with CertsForce

Viewing page 2 out of 6 pages
Viewing questions 11-20 out of questions
Questions # 11:

Transformers & Rectifiers Ltd wanted to buy some specialist gaskets. They sent a request for quotation with specification to Needs Ltd. The supplier replied with a quotation in which had its own terms and conditions. The buyer edited delivery terms on the quotation and sent the document back to Needs Ltd. Gaskets were delivered to Transformers’ premise with an invoice from Needs Ltd. Which of the following is most likely to be the governing terms if the two companies must settle the dispute at court?

Options:

A.

Edited terms and conditions


B.

Terms and conditions in the request for quotation


C.

Terms and conditions in the invoice


D.

Terms & conditions in the original quotation


Expert Solution
Questions # 12:

A construction company is undertaking a housing development project. They need lots of bricks and other building materials, but the construction site doesn't have large area for storage of materials.Therefore, the company's suppliers must deliver the building materials with fixed quantity and at fixed time intervals. What type of contract is used between the construction company and its suppliers?

Options:

A.

Framework agreement


B.

Spot transaction


C.

One off contract


D.

Call off contract


Expert Solution
Questions # 13:

A fashion company is drafting a specification for an order in next year. The company wants to expand its supply base in low cost countries. The procurement department is considering applying standard ISO 3759 on method for the preparation, marking and measuring of textile fabrics, garments and fabric assemblies for use in tests for assessing dimensional change after a specified treatment. Which of the following should be taken into account when embedding this standard into the specification?

Options:

A.

Date of publication


B.

Supplier selection


C.

Type of specification


D.

Legality


Expert Solution
Questions # 14:

Which of these describes “consideration” within a contract?

Options:

A.

The communication of an unconditional agreement


B.

Both parties exchange something of value


C.

The desire of both parties to enter into a contract


D.

Ability of both parties to be able to enter into a contract


Expert Solution
Questions # 15:

Which of the following are examples of express terms in a contract? Select TWO that apply.

Options:

A.

A retention of title term


B.

Term inserted by the Sale of Goods Act 1979


C.

A liquidated damages term


D.

Term inserted through business efficacy test


E.

Term inserted through the custom of the trade


Expert Solution
Questions # 16:

Cleveland Insurance (Cleveland) offers a range of insurance services. The main software used in the call centre is a customer relationship management (CRM) system. Cleveland perceived an urgent need to replace the existing CRM system to deal with the increasing number of customers and services.

Urgent Digital Ltd (Digital) is one of the bidders of Cleveland’s ITT for designing, building and managing the new CRM system. Its bid team is led by Hank Irvine, its technical director. Hank realises that winning the Cleveland contract (valued at approximately £50M) will enhance his career. During discussions with Cleveland, Hank offers certain assurances regarding timescales for the project. He has not carried out any investigations into the viability of the timescales. Hank has little idea whether the timescales can be met.

Cleveland decides that Digital’s bid meets with its requirements, especially given the assurances in timescale offered by Hank, and decides to proceed with it, subject to a formal contract. Eventually, a formal contract is signed by both parties. The initial assurances given by Hank about the timing of the project are never going to be achieved and are at best grossly exaggerated.

Cleveland brought the case to the court and sought rescission of contract with Digital. Is Cleveland’s claim appropriate in this case?

Options:

A.

Yes, because Cleveland needs to seek rescission first before claiming for damages


B.

Yes, because both parties agreed with rescission of their contract


C.

No, because the work had been carried out which could not be returned


D.

No, because the contract does not include any provision on rescission


Expert Solution
Questions # 17:

A retailer prefers to display its best selling products and promotion programme on the building windows. According to rule of contract formation, this act will generally constitute...?

Options:

A.

An invitation to treat


B.

A legal capacity


C.

An offer


D.

A mailbox rule


Expert Solution
Questions # 18:

Which of the following approaches could a purchasing organisation use to reduce the level of detail in a specification, without increasing the risk of an unsuccessful procurement process?

Increase the use of acronyms and abbreviations

Cross-refer to recognised industry standards

Require tendering suppliers to propose specifications

Provide samples to demonstrate the requirements

Options:

A.

1 and 3 only


B.

2 and 4 only


C.

2 and 3 only


D.

1 and 4 only


Expert Solution
Questions # 19:

Buyer D agrees a contract with Supplier C which includes the words 'to be agreed' in relation to the date for delivery of the goods. At the time of the contract, Buyer D is aware that the goods take two days to produce and one day to deliver. Buyer D contacts the supplier one week later, requesting the goods be delivered the following day. Supplier C is unable to deliver the next day but rather delivers the goods three days later. Is it the case that Buyer D can legally refuse to pay for the goods because Supplier C is in breach of contract?

Options:

A.

Yes, because the delivery date is an express term within the contract


B.

Yes, because the goods should have been delivered within three days


C.

No, because the goods were delivered within a reasonable time


D.

No, because there is a contract in place and the delivery date does not matter


Expert Solution
Questions # 20:

Which of the following is used to detail the complex matter that may be verbiage to the main document?

Options:

A.

Contract variation


B.

Schedule


C.

Subcontracting


D.

Standard terms and conditions


Expert Solution
Viewing page 2 out of 6 pages
Viewing questions 11-20 out of questions