CIPS Commercial Contracting L4M3 Question # 18 Topic 2 Discussion

CIPS Commercial Contracting L4M3 Question # 18 Topic 2 Discussion

L4M3 Exam Topic 2 Question 18 Discussion:
Question #: 18
Topic #: 2

Which of the following should be done by procurement professionals right after obtaining a pre-written specification for a critical item so that the added value will be the greatest?


A.

Evaluate tender or quotation


B.

Select the best supplier


C.

Challenge the used specification


D.

Issue invitation to tender or request for quotation