Questions # 31:

What is the recommended placement of electrical distribution sub systems

Options:

A.

install in dedicated electrical rooms, or, locate outside the computer room with fire rated wall


B.

install within the computer room space on raised floor


C.

install within server racks


D.

none of the above


Expert Solution
Questions # 32:

What is the high temperature that must be maintained in a data center according to TIA-942?

Options:

A.

70 degrees


B.

75 degrees


C.

77 degrees


D.

80 degrees


E.

85 degrees


Expert Solution
Questions # 33:

What is the recommended range for the high temperature in a data center according to NEB?

Options:

A.

80 degrees


B.

75 degrees


C.

85 degrees


D.

70 degrees


E.

90 degrees


Expert Solution
Questions # 34:

what is the ANSI/TIA-942 typical range of pressure differential regarding positive pressure for data center.

Options:

A.

Less than or equal to –0,1 in water column (-25 Pa)


B.

More than -0,005 in wc (< -1,24 Pa), but less than or equal to +0,05in wc (+12,4 Pa)


C.

More than +3in wc (>746Pa),but less than or equaltto+6,in wc(1492 pa))


D.

Less Than –4,+4 inches water column(-1000 opa ,+100 )


Expert Solution
Questions # 35:

what is the most common energy storage solution and what are the two types

Options:

A.

Lithium-ion battery, sealed and unsealed


B.

Flywheel, vertical and horizontal


C.

Supercapacitor, cylindrical and prismatic


D.

Lead-acid battery, vented and valve regulated

Nickel-cadmium battery, vented and valve regulated


Expert Solution
Questions # 36:

What is the acceptable rate of temperature change per hour in a data center according to TIA-942?

Options:

A.

5 degrees


B.

7 degrees


C.

9 degrees


D.

12 degrees


E.

15 degrees


Expert Solution
Questions # 37:

Where should telecom cabling be routed under an access floor?

Options:

A.

In the cold aisle


B.

Above the access floor


C.

In the plenum space


D.

In the equipment room


E.

In the office area


Expert Solution
Questions # 38:

Apart from marine cargo ports, hazardous material transport roadways, transportation roadways, and flight paths, what other things should a data centre be at least one mile away from?

Options:

A.

Waste-disposal units and dumpsites only.


B.

Petroleum storage installations like petrol stations & oil storage facilities only.


C.

Fireworks manufacturing companies only.


D.

All of The Above


Expert Solution
Questions # 39:

What is the preferred location of the power distribution unit?

Options:

A.

a service gallery outside the computer room, if the A H J and feeder distances allow


B.

under each server rack


C.

in an unused area of another floor


D.

inside a ventilation duct


Expert Solution
Questions # 40:

What is the appropriate fire rating requirements for an electrical room?

Options:

A.

1/2 hour


B.

1 hour


C.

2 hours


D.

3 hours