BICSI Data Center Design Consultant – DCDC DCDC-002 Question # 31 Topic 4 Discussion

BICSI Data Center Design Consultant – DCDC DCDC-002 Question # 31 Topic 4 Discussion

DCDC-002 Exam Topic 4 Question 31 Discussion:
Question #: 31
Topic #: 4

What is the recommended placement of electrical distribution sub systems


A.

install in dedicated electrical rooms, or, locate outside the computer room with fire rated wall


B.

install within the computer room space on raised floor


C.

install within server racks


D.

none of the above


Get Premium DCDC-002 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.