Questions # 1:

A Scrum Team is required to deliver a Done Increment by the end of a Sprint. Select two statements that explain what Done means. (choose the best two answers)

Options:

A.

Ready to be released to end users.


B.

Whatever the Product Owner defines as quality.


C.

No work is left to meet the Definition of Done.


D.

Ready for integration.


E.

All work the Developers are willing to do.


Expert Solution
Questions # 2:

What would not be considered refactoring?

Options:

A.

Extracting methods


B.

Reordering method parameters to improve readability


C.

Changing external interfaces or APIs


D.

Renaming things to be more logical


E.

Extracting interfaces


Expert Solution
Questions # 3:

What statement best describes the product backlog?

Options:

A.

It is an emergent, ordered list of what is needed to improve the product


B.

It is the diary of the product owner


C.

It is mainly meant as inspiration for the sprint planning


D.

It is a list of all the requirements that will have to be added to the product


Expert Solution
Questions # 4:

When should a newly discovered huge bug of a previous sprint be fixed?

Options:

A.

Immediately.


B.

Don't fix it immediately, but change the test to not show it as a temporary fix.


C.

Don't fix it, but stub out the code that causes it.


D.

Depends on what the product owner wants.


Expert Solution
Questions # 5:

What does a test written with TDD represent?

Options:

A.

A technical requirement that must be satisfied


B.

A bug


C.

Great development practices


D.

Something that completes the test coverage of a system


Expert Solution
Questions # 6:

When are testers and QA experts ideally included in the project?

Options:

A.

After every sprint review


B.

From the beginning and throughout the sprints, but let's call them developers


C.

When the developers are done


D.

When the product is complete


Expert Solution
Questions # 7:

Who creates tests on a Scrum Team? (choose the best answer)

Options:

A.

The Scrum Master.


B.

The Product Owner.


C.

Quality Assurance Specialists.


D.

The Developers.


Expert Solution
Questions # 8:

While developing new functionality, you find a bug that has already been delivered to the customer. What do you do?

Options:

A.

Fix the bug


B.

Revise the tests to hide the bug from the tests reports


C.

Talk to the product owner


D.

Stub out the code that causes the bug


Expert Solution
Questions # 9:

Why might a scrum team choose to do pair programming?

Options:

A.

Improving code quality


B.

All of these


C.

It is a nice way to work


D.

Information sharing and learning


E.

Efficiency


Expert Solution
Questions # 10:

What is a sprint burn down chart?

Options:

A.

Visual representation of work that is still to do and time that is left


B.

A chart showing progress towards the product goal


C.

A chart that shows whether bugs came up


D.

Visual representation of the product backlog items left