Questions # 31:

Which of the following SAFe Core Competencies of Business Agility includes the built-in quality dimension?

Options:

A.

Agile Product Delivery


B.

Team and Technical Agility


C.

Organizational Agility


D.

Enterprise Solution Delivery


Expert Solution
Questions # 32:

What is the recommended length of an Iteration?

Options:

A.

Two weeks


B.

Ten weeks


C.

Four weeks


D.

Eight weeks


Expert Solution
Questions # 33:

A cumulative flow diagram focuses on which curves?

Options:

A.

Arrival curve ("to do") and evolution curve ("change")


B.

Implementation curve ("movement") and departure curve ("done")


C.

Backlog curve ("work") and departure curve ("done")


D.

Arrival curve ("to-do") and departure curve ("done")


Expert Solution
Questions # 34:

Which of the following Agile Team responsibilities is associated with the Iteration Retrospective?

Options:

A.

Improve relentlessly


B.

Apply systems thinking


C.

Take an economic view


D.

Connect to the customer


Expert Solution
Questions # 35:

Which statement is true about pair work in the Scaled Agile Framework?

Options:

A.

It comes from pair programming in Extreme Programming (XP)


B.

It is a best practice that team members should spend 50% to 100% of the time in pair work


C.

It occurs during Iteration Planning


D.

It is for developers only


Expert Solution
Questions # 36:

A User Story includes which three things? (Choose three.)

Options:

A.

Who


B.

Level of Risk


C.

Why


D.

What


E.

Definition of Done


F.

How


Expert Solution
Questions # 37:

During which PI planning activity are Stories written and sequenced?

Options:

A.

The team breakout session


B.

The draft plan review


C.

The management Review and Problem-Solving workshop


D.

The business context presentation


Expert Solution
Questions # 38:

What is the role of the System Architect/Engineer?

Options:

A.

To manage dependencies


B.

To implement continuous improvement methods


C.

To guide the teams and support the Architectural Runway


D.

To define the design for the system


Expert Solution
Questions # 39:

Which of the following measures tracks progress toward achieving desired outcomes?

Options:

A.

Burn-down charts


B.

Cumulative flow diagrams


C.

Objectives and key results


D.

ART actual business value


Expert Solution
Questions # 40:

What best describes the process of the confidence vote?

Options:

A.

Business Owners vote


B.

The teams and the ARTs vote


C.

The managers vote


D.

Each person votes


Expert Solution