An Iteration is a fixed timebox during which an Agile team delivers a potentially releasable increment of value. The recommended length of an Iteration is two weeks, as this allows for fast feedback, adaptation, and learning cycles. Longer Iterations may increase the risk of overcommitment, scope creep, and reduced quality. Shorter Iterations may increase the overhead of planning and coordination, and reduce the amount of value delivered per Iteration. References: Exam Study Guide: SP (6.0) - SAFe® Practitioner, [Iteration]