Pass the Nutanix Nutanix SE Academy NCSC-Level-1 Questions and answers with CertsForce

Viewing page 1 out of 3 pages
Viewing questions 1-10 out of questions
Questions # 1:

A customer has engaged a Nutanix consultant to deploy a cluster consisting of two NX-3460-G6 blocks. The consultant arrives at the customer site and fines the following:

* One rack with a total of 5U available

* Two ToR switches with 14 total available ports

* Dual PDUs with six available sockets

What will prevent the consultant from successfully installing the cluster?

Options:

A.

Insufficient sockets for power allocation.

Rack space may not be continuous.


B.

Insufficient rack space for block installation.

Insufficient sockets for power allocation.


C.

Insufficient network ports for communication.

Insufficient sockets for power allocation.


D.

Insufficient network ports for communication.

Insufficient sockets for power allocation.


E.

Insufficient network ports for communication.

Rack space may not be continuous.


Questions # 2:

A consultant successfully completes a Foundation using a flat switch. The consultant then works with the customer to move the cluster over to their production network. After the move, the CVMs and hypervisors can no longer communicate, which prevents the cluster from starting.

Which option should be used to resolve this issue?

Options:

A.

If the IPMI is in use, check that the IPMI can ping the default gateway over IPv6.


B.

Make sure that the IPMI and CVM VLAN is manually tagged on the Host and CVM.


C.

Verify that IPv6 Link Local and DHCP is enabled on all switch ports.


D.

If using VLANs, confirm the hypervisor/CVM VLAN is set as Native on the switch ports.


Questions # 3:

Which two components must be identified to validate that software compatibility requirements are met for Nutanix Cluster Installation? (Choose two.)

Options:

A.

Guest OS


B.

AOS


C.

Firmware


D.

Hypervisor


Questions # 4:

A consultant is viewing an ESXi host via console without external network connectivity.

Which two IP addresses can be used to connect to the CVM (Choose two.)

Options:

A.

192.168.5.253


B.

192.168.5.2


C.

192.168.5.254


D.

192.168.5.1


Questions # 5:

A consultant creates a Windows VM after installing a new Nutanix cluster running AHV. The consultant has statically assigned an IP address to the VM but it is unable to communicate on the network.

Which action should the consultant take to resolve this issue?

Options:

A.

Confirm that IPv6 is enabled on the guest VM.


B.

Confirm that the VM vNIC is tied to the correct VLAN in Prism Element.


C.

Mount and install the Nutanix Guest Tools.


D.

Set a Group Policy to make sure the Windows Firewall is disabled.


Questions # 6:

A consultant deploys a four-node VMware ESXi cluster and vCenter server. An HA/DRS cluster is configured for all four nodes. The customer deploys five new VMs on the cluster.

During the knowledge Transfer, a network cable on one node is removed to demonstrate HA and migration of the VMs to another host. In the HA/DRS cluster settings, the VM Restart Priority for all CVMs is set to Disabled. The customer observes warnings that the CVM on the ejected host is no longer powered on.

Which ESXi HA/DRS cluster setting is missing?

Options:

A.

Enable EVC for the cluster.


B.

Disable VM Monitoring on all CVMs.


C.

Disable Automation Level on all CVMs.


D.

Enable Host Monitoring.


Questions # 7:

A consultant is running the Foundation VM using desktop virtualization software. No nodes are discovered.

What should the consultant verify first?

Options:

A.

NAT


B.

Host-only Adapter


C.

Bridged Adapter


D.

Internal Network


Questions # 8:

A consultant is imaging a Nutanix cluster with VMware ESXi. Foundation returns an error that the media is not a supported ISO. The consultant checks the whitelist file in Foundation and confirms that the version of the ISO is not listed.

Which three actions should the consultant take to resolve this issue? (Choose three.)

Options:

A.

Replace and save whitelist file in Foundation


B.

Obtain the MD5 checksum of the ISO and confirm MD5 checksum of ISO is listed.


C.

Download the iso_whitelist.json from the Support portal.


D.

Edit the whitelist file in Foundation.


E.

Restart the imaging process in Foundation.


Questions # 9:

A customer wants to use NIC teaming on an ESXi host using a vSphere Standard Switch configured with the Route based on physical NIC load load balancing option. The customer does not see the option when editing the Teaming and Failover settings for the switch.

How should the consultant resolve this issue?

Options:

A.

Change the load balancing option on the switch.


B.

Add a vSphere Distributed Switch


C.

Add another physical NIC to the team.


D.

Install a vCenter server to manage the switch


Questions # 10:

To prepare for a new Nutanix installation, a consultant downloads the Foundation VM, imports the VM to their Desktop Virtualization Solution, and powers on the VM. The IPv4 static address on the host workstation and the Foundation VM have been configured, but pings between them fail.

Which two troubleshooting steps should the consultant perform? (Choose two.)

Options:

A.

Remove and re-import the Foundation VM to ensure the virtual NIC is set to Host-Only.


B.

Verify the virtual NIC in the Foundation VM is bound to the correct physical Host adapter.


C.

Confirm the IP addresses and subnet masks are correct.


D.

Verify the virtual NIC in the Foundation VM is bound to the correct wireless network adapter.


Viewing page 1 out of 3 pages
Viewing questions 1-10 out of questions