Questions # 31:

You need to configure the system to support the pottery product line. What should you do first?

Options:

A.

Create a new product with storage dimensions.


B.

Create a new product master with predefined product variants.


C.

Create a new product with lucking dimensions.


D.

Set up a new product with product configuration.


Expert Solution
Questions # 32:

You need to configure the system to support the pottery line.

What should you do first?

Options:

A.

Set up a new product with product configuration.


B.

Create a new product with tracking dimensions.


C.

Create a new product master with pre-defined product variants.


D.

Create a new product with storage dimensions.


Expert Solution
Questions # 33:

You need to configure settlement reports for the finance team.

Which processes should you use? To answer, select the appropriate options in the answer area.

NOTE: Each correct selection is worth one point.

Question # 33


Expert Solution
Questions # 34:

You need to address the inventory cost requirements.

What are two possible ways to achieve the goal? Each answer represents a complete solution.

NOTE Each correct selection is worth one point

Options:

A.

Set up a costing sheet


B.

Set up commodity pricing.


C.

Use FIFO with marking.


D.

Create a costing version.


E.

Create purchase orders from sales orders.


Expert Solution
Questions # 35:

You need to configure the system to support regional sales requirements.

Which group assignments should you use? To answer, select the appropriate options in the answer area.

NOTE. Each correct selection is worth one point.

Question # 35


Expert Solution
Questions # 36:

You need to configure the system to meet the metric requirement for sales representatives.

How should you configure the system? To answer, drag the appropriate entities to the correct requirements. Each entity may be used once, more than once, or not at all. You may need to drag the split bar between panes or scroll to view content.

NOTE: Each correct selection is worth one point.

Question # 36


Expert Solution
Questions # 37:

You need to configure the system to support the inventory costing requirement.

Which two actions should you perform? Each answer represents a complete solution.

NOTE: Each correct selection is worth one point.

Options:

A.

one default item group for all items


B.

one item group each for perfume, ceramicware, and other goods


C.

one FIFO item model group and one Standard item model group


D.

one FIFO item group


E.

one financial dimension for each item group


Expert Solution
Questions # 38:

You need to configure the system to meet the item testing requirements.

How should you configure the system? To answer, select the appropriate options in the answer area.

NOTE: Each correct selection is worth one point.

Question # 38


Expert Solution
Questions # 39:

You need to identify the cause for the inventory issue reported by customer service representatives.

What is the root cause?

Options:

A.

Run inventory close process.


B.

Ordered reserved box should be checked, this will disable quantities.


C.

Turn on automatic reservation.


D.

Ordered reserved quantity is due to marking.


E.

Turn off automatic reservation.


Expert Solution
Questions # 40:

You need to configure the system to meet the inventory team cost control requirement.

Which processes should you run? To answer, drag the appropriate processes to the correct requirements. Each process may be used once, more than once, or not at all. You may need to drag the split bar between panes or scroll to view content.

NOTE: Each correct selection is worth one point.

Question # 40


Expert Solution
Viewing page 4 out of 7 pages