This is the correct order of the LEED certification process for most projects1. The first step is to register the project on LEED Online and pay the registration fee2. The second step is to prepare the application by collecting and uploading the required information and documents according to the chosen rating system and credits2. The third step is to submit the application and pay the certification fee2. The fourth step is to undergo the application review by a LEED accredited third party, which may request clarifications or corrections2. The final step is to receive the certification decision and the LEED plaque and certificate2.
Life-cycle cost analysts of a new construction includes consideration of
cost of purchasing window glazing
cost of adding accessible parking
cost of challenging a real estate tax assessment
cost of subsidizing the use of public transportation
Answer: A
Life-cycle cost analysis (LCCA) is a method for assessing the total cost of owning a facility or running a project. It considers all the costs associated with obtaining, owning, and disposing of an investment1. The cost of purchasing window glazing is one of the initial costs that affects the energy performance and thermal comfort of a building2. Therefore, it is included in the LCCA of a new construction.
Chosen Answer:
This is a voting comment (?). You can switch to a simple comment. It is better to Upvote an existing comment if you don't have anything to add.
Submit