Which statement about Requirements Management Is most correct?
Stakeholder Requirements are captured once in Phase A and managed throughout the ADM cycle.
Requirements management and stakeholder engagement are placed at the center of architecture development.
Requirements Management is a step of all ADM Phases.
The purpose of Requirements management is to process change requests.