Question #: 48
Topic #: 5

Complete the sentence. The Requirements Management Phase _____________________.


A.

addresses and resolves requirements between ADM phases


B.

is a central process that prioritizes requirements for all ADM phases


C.

is used to dispose of resolved requirements for all ADM phases


D.

generates new requirements and passes them to all ADM phases


E.

stores requirements and manages their flow into relevant ADM phases